As the construction team is back in full force after the holidays, work continues to close in the building. The masons are completing their work on the building. They will then begin laying the block for our 2 signage walls on the north and south entries of the church parking lot, after the concrete footings are poured.
The pouring of the Sanctuary steps and flooring will begin within two weeks. Followed by the signage wall footings.
A crane was brought in to install the 72 foot beams above the Sanctuary area. The layout of the future air conditioning duct work layout has been completed. The concrete saw cutting should begin next week allowing the duct work to pass through the internal walls.
The aluminum window frames are scheduled to arrive on March 7. The bell tower louvers will arrive on March 11. Saw cutting for the stained glass exterior windows will begin within 2 weeks