The framing of the Sacristy areas has begun.
The Sanctuary area is scheduled to have the concrete poured today, Friday at 5am. The trusses for the transepts are being constructed onsite. The Chapel area demolition is continuing.
Next week will be the start for a number of areas. The contents of the offices were moved out and stored so the upgrade can begin in that area. Also beginning, the saw-cutting of the block in the Narthex to allow space for the new air conditioning ductwork, and the site grading and curbing for the southside drop off.
This week's photos: