December 9

12-09-2022Church Building Update

The new mechanical sub is onsite today to finalize the layout for the saw cuts through the block for the additional A/C ductwork.

The plumbing leak that was discovered last week has been located. It will be fixed when the plumbing team is onsite to install the main storm drain on the east side of the construction project. This will occur during St. John Bosco's Christmas break. We will be trenching down the center of the driveway which is between the new worship space and the Annex buildings.

The bell tower has one more "lift" to complete the block work. The transepts are ready for steel. The metal stud framers will be building the trusses next week.

The parking lot lights on the north side will be repaired next week.
Even with the issues resulting from the need to replace the mechanical sub, we are still on target for a Q3 2023 completion.

This week's photos:

  • The bell tower arches taking form.
  • A look up the inside of the bell tower.
  • The south side of the building.