The masons are on their third lift for the tower and elevator construction. The north arch entry is in the process of being completed.
The south side sewer is in. The north side sewer is ready for inspection. The plumber will start on installing the new major fire line feeder pipe next week.
At 6:00am on Monday the final steel for the mezzanine will be delivered. By the end of next week we should have a mezzanine steel structure.
The project is on schedule for a Q3 completion.
Photos for this week: